RoadTek is being engaged to complete rehabilitation works on the Gregory Developmental Road (98B Belyando – Charters Towers). These works are anticipated to commence in July 2020, which necessitates the procurement for the supply and delivery of quarry materials.
The intended work cycle will be 10 on 4 off, Tuesday to 2nd Thursday with daily hours of 6.30am – 5.30pm. Submitted rates need to take into account the work cycle including Saturday and Sunday material delivery requirements.
RoadTek will require up to 700 tonne/day on carting days. It is critical that 700 tonnes can be delivered between 7.00am – 3.00pm on site, on the required days.