The Queens;land Goivernment is seeking proposals for a Principal Contractor to install 4 electricty generators at Queensland Health sites which are located at Darnley, Kubin, St Pauls and Warraber. These generators provide backup power to Primary Health Care Centres, which are in the above locations.
The generators are currently being constructed in Cairns and will be delivered to the above locations as part of the supply contract. They are expected to arrive at site in November 2022 and will be weather protected and stored in readiness for installation.
The Principal Contractor's roles involves the following:
Construction of concrete bases
Installation of generator onto concrete bases
Electrical and BMS connections to the Primary Health Care Centre
Removal of existing gen sets and site tidy up
Testing and Commissioning
Servicing through the defects liability period
First fill of fuel.